Section 31. Retail Competition and Open Access. —

Any law to the contrary notwithstanding, retail competition and open access on distribution wires shall be implemented not later than three (3) years upon the effectivity of this Act, subject to the following conditions:

  1. Establishment of the wholesale electricity spot market;

  2. Approval of unbundled transmission and distribution wheeling charges;

  3. Initial implementation of the cross subsidy removal scheme;

  4. Privatization of at least seventy (70%) percent of the total capacity of generating assets of NPC in Luzon and Visayas; and

  5. Transfer of the management and control of at least seventy percent (70%) of the total energy output of power plants under contract with NPC to the IPP Administrators.

Upon the initial implementation of open access, the ERC shall allow all electricity end-users with a monthly average peak demand of at least one megawatt (1MW) for the preceding twelve (12) months to be the contestable market. Two (2) years thereafter, the threshold level for the contestable market shall be reduced to seven hundred fifty kilowatts (750kW). At this level, aggregators shall be allowed to supply electricity to end-users whose aggregate demand within a contiguous area is at least seven hundred fifty kilowatts (750kW). Subsequently and every year thereafter, the ERC shall evaluate the performance of the market. On the basis of such evaluation, it shall gradually reduce the threshold level until it reaches the household demand level. In the case of electric cooperatives, retail competition and open access shall be implemented not earlier than five (5) years upon the effectivity of this Act.