Section 34. Objective and Process of Post-qualification. —
Post-qualification is the stage where the bidder with the Lowest Calculated Bid, in the case of Goods and Infrastructure Projects, or the Highest Rated Bid, in the case of Consulting Services, undergoes verification and validation whether he has passed all the requirements and conditions as specified in the Bidding Documents.
If the bidder with the Lowest Calculated Bid or Highest Rated Bid passes all the criteria for post-qualification, his Bid shall be considered the "Lowest Calculated Responsive Bid," in the case of Goods and Infrastructure or the "Highest Rated Responsive Bid," in the case of Consulting Services. However, if a bidder fails to meet any of the requirements or conditions, he shall be "post-disqualified" and the BAC shall conduct the post-qualification on the bidder with the second Lowest Calculated Bid or Highest Rated Bid. If the bidder with the second Lowest Calculated Bid or Highest Rated Bid is post-disqualified, the same procedure shall be repeated until the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid is finally determined.
In all cases, the contract shall be awarded only to the bidder with the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid.